Rédiger un scénario de recette ERP industriel

Décrire ce qui doit fonctionner avant de juger ce qui fonctionne.
September 30, 2026 by
Rédiger un scénario de recette ERP industriel
OdooBot

Acceptance starts before configuration

Acceptance criteria are written during scoping, not the day before cutover. They are then used to judge the trial, the pilot and every upgrade.

Diagram — Acceptance testing runs through the project, from scoping to upgrades.
  1. ScopingWritten acceptance criteria
  2. TrialScenario on fictitious data
  3. PilotReal data, one scope
  4. Blocking gap?Yes: fix and retest. No: signed acceptance record.
  5. Go-liveAcceptance rerun at every upgrade

The structure of a step

  • Step identifier and title.
  • Role that performs it.
  • Starting data.
  • Action to perform.
  • Expected result, verifiable by a third party.
  • Status: compliant, minor gap or blocking gap.

An example

Step B-03: the production manager launches the manufacturing order for 20 units from the sales order. Expected result: components reserved, operations scheduled on the right work centers, planned cost displayed.

Covering the difficult cases

Component shortage, scrap, rework, partial quantity, cancellation, subcontracting and correction of an entry error: these cases reveal more defects than the nominal flow.

Recording the gaps

Each gap gets a severity, an owner, a decision and a date. The signed acceptance record lists the accepted gaps and those that block go-live.

Limits

An acceptance scenario checks expected behavior; it measures neither performance under load nor security, which need their own tests.