Three different questions
The master production schedule answers “how much of each family to produce, week by week?”. Net requirements planning answers “which components to buy or make, and when?”. Replenishment answers “when to top up a standard item?”.
Master schedule
- Product families
- Horizon of several months
- Enterprise edition
Requirements planning
- Bills of materials and lead times
- Proposed purchases and orders
- Make-to-order
Replenishment
- Min/max rules
- Standard items
- Community edition

In Odoo
- Min/max replenishment rules and manufacture or buy routes are in Community.
- Make-to-order triggers orders linked to a sales order.
- The master production schedule belongs to the Enterprise edition.
Choosing the right level
Make-to-order production with few items often relies on make-to-order and replenishment of standard components. Make-to-stock production with seasonal peaks justifies a master schedule.
Limits
None of these mechanisms automatically accounts for finite work center capacity. The result remains a proposal to be arbitrated.