Maintenance et planning : bloquer un poste sans casser la production

Rendre les arrêts visibles avant qu’ils ne surprennent l’atelier.
September 30, 2026 by
Maintenance et planning : bloquer un poste sans casser la production
OdooBot

The problem

Preventive work planned without production knowing, and an urgent order is blocked; an undeclared breakdown, and the schedule promises impossible lead times.

Diagram — Coordinating maintenance and production by edition.
  • Odoo Community

    Core

    • Request calendar
    • Manual work center block
  • Odoo Enterprise

    With an Odoo Enterprise licence

    • Request linked to the work center
    • Graphical planning
  • Organization

    To be assessed

    • Joint weekly review
    • Human arbitration
Maintenance calendar for press P07, week 40: lubrication on Wednesday, monthly preventive on Sunday
The maintenance week: the open requests for one piece of equipment, here press P07, placed on a shared calendar. Screenshot from an Odoo 20 test database, fictitious company Mécanique Exemple SAS, September 28, 2026.

In Odoo Community

  • Maintenance requests have a scheduled date and a calendar view.
  • A work center can be blocked manually, with a stoppage reason.
  • The automatic link between a maintenance request and the work center belongs to Enterprise.

A simple rule

Each week, maintenance and production review the request calendar and the orders of the work centers concerned together. The block is set at the time of the intervention and lifted when it closes.

Limits

Blocking a work center does not automatically reschedule orders that are already planned: the trade-off remains human.

Sources

Odoo — Maintenance documentation

See the machine fleet case