La bascule ERP : un plan heure par heure

Geler, reprendre, vérifier, décider : la bascule se prépare comme une opération.
September 30, 2026 by
La bascule ERP : un plan heure par heure
OdooBot

Before cutover

Two successful dry-run migrations, a backup restored and tested, trained users and a signed rollback criterion. Without these four conditions, the date is postponed.

Diagram — The course of a cutover and its decision gate.
  1. FreezeNo more entries in the old system
  2. MigrationMaster data and open items
  3. ReconciliationQuantities and values
  4. Go live?Yes: start. No: rollback.
  5. MonitoringFirst operations tracked

The typical plan

  1. Freeze entries in the old system and count work in progress.
  2. Extract, migrate and check master data.
  3. Migrate open items: stock, orders, manufacturing orders.
  4. Reconcile quantities and values with the old system.
  5. Go-live or rollback decision.
  6. First real operations under close monitoring.

Checkpoints

Each step has an owner, a deadline and a verifiable result. A reconciliation gap not explained by the planned time triggers the decision, not a silent extension.

Limits

Durations depend on data volume and the number of sites; we set them after the dry runs, never before.

See the project method

Plan directeur, calcul des besoins, réassort : qui fait quoi ?
Trois niveaux de planification à ne pas confondre.